the challenge
The sunshade structures were drawn with steel framing and aluminum infills. This would require us to work in unison with the steel fabricator and our measurements would have to be spot on.
the solution
We went through several rounds of submittals with the architect, filling in the missing details and making sure we were fulfilling their design intent. We verified placement of all the steel tabs with the steel fabricator and custom fabricated our product incorporating those dimensions. The heavy project management work and submittal detailing ultimately led to the successful completion of the Hollyhock Amenity Center.
the client
the details
1”x3” shutter blades
Custom hole framing for lights
Install of sunshades was expedited and complete in 5 days onsite